Crompton have the experience and expertise to review your entire DA conditions to what is required for approval at CMP DA Level and even submit online on your behalf.
At CMP Stage, you may require the following to be approved, which Crompton can assist with:
- Stamped CMP DA Approval
- Tree Removals
- 24/7 or Daily Footpath Closures
- Translink/Bus Stop
- Advertising Signs
- RPEQ
Approvals at CMP can take up to 20-40 business days, it is Crompton's recommendation to do a pre-lodgement meeting for any complex sites that require approvals that is outside council standard approvals. Pre-lodgements can take up to 3-4 weeks for the meeting, however this reduces the RFI’s at CMP and redesigning. Once you have received your DA approval, we can submit your initial road permit – this can take up to 30 business days.
GOLD COAST COUNCIL
Crompton can review your decision notice to what is required to be submitted for approval. (We can process these on your behalf online.)
At CMP/LONO (Letter of no objection), you may require the following to be approved which we can assist with:
- CMP Approval through Development Services
- LONO Approval through TRC
- Tree Removals
- Any Footpath Closures
- Translink/Bus Stop
- Advertising Signs
- RPEQ
These approvals at CMP/LONO can take up to 2 business days, and once the approval is received we can submit your initial operational permit which can take 20 business days.
TMR
SARA Approval (TMR Frontage) 20 – 30 business days, Crompton can submit your traffic management documents and CMP through to TMR and they will come back with an RFI or an approval to submit TCP and RCP.
Section 33 (TMR frontage but breaking ground for a permanent arrangement e.g. crossover for construction access) This process can take up to 4 months for approval; Crompton can submit your traffic management and CMP. TMR will require a bond for the works being conducted.